How long does a high-end bathroom renovation take? A week-by-week guide

"How long will we be without a bathroom?" is one of the first questions we are asked. The honest answer is that it depends on the size of the room, how much is changing and how quickly materials arrive. This guide shows how a typical high-end bathroom or en-suite renovation runs, so you know what to expect.
Before work starts: design and ordering
The planning stage often takes longer than the building work, and it is where most delays can be avoided.
Design and layout: decide where the shower, bath, basins and toilet go before anything is ordered, because moving waste pipes later is costly. Our guide to planning a family bathroom or en-suite layout can help.
Lead times: bespoke vanity units, made-to-measure glass screens, some tiles and designer brassware can take several weeks to arrive. We like everything on site, or with a confirmed delivery date, before we start.
Decisions made up front: tiles, grout colour, tap finishes and the position of every socket, shaver point and light should be agreed before strip-out.
A typical week-by-week plan
For a principal en-suite or family bathroom, this is a common sequence:
Week 1, strip-out and first fix: the old suite, tiles and often the floor come out. Any damaged floorboards or joists are repaired, and new pipework, waste runs and electrical cables are installed while the walls and floor are open.
Week 2, walls, floors and waterproofing: walls are boarded or plastered, wet areas are waterproofed (tanked), and underfloor heating and any screed are laid. A screed needs time to dry before it can be tiled, so this can add days.
Week 3, tiling: wall and floor tiling, then grouting. Large-format and natural stone tiles take longer to lay well than standard tiles.
Week 4, second fix and finishing: the basin, toilet, bath, shower valve, glass screen, towel rail, mirrors and lights are fitted, everything is sealed and tested, and the room is decorated.
A smaller en-suite with a like-for-like layout is often finished in two to three weeks. A large family bathroom, a full wet room or a project that moves walls can take four weeks or more.
What can stretch the timeline
Wet rooms: the whole floor has to be waterproofed and laid to a fall towards the drain, which adds work. Our guide to wet rooms and walk-in showers explains the difference.
Underfloor heating: electric mats are quick; a wet system connected to the heating may need a screed and drying time. Read electric or wet underfloor heating.
Hidden problems: rotten joists, old lead pipework or poor wiring are sometimes only found when the room is stripped.
Electrics: most electrical work in a bathroom is notifiable under Part P of the Building Regulations and must be certified. Our sister company, The Essential Connection, handles and certifies it.
Living with the work
If it is your only bathroom, we can plan the order of work so a toilet is out of action for as short a time as possible.
We protect floors and stairs and seal off the room to keep dust down.
Good ventilation is designed in from the start, which prevents mould and condensation later.
Plan your bathroom with Koniu
Koniu Construction designs and builds high-end bathrooms and en-suites in Walton-on-Thames, Hersham, Burwood Park, Ashley Park, Cobham and Stoke d'Abernon. Read about our bathroom renovations in Ashley Park and Burwood Park and what a high-end bathroom costs, call 07434 781033, or contact us to arrange a visit.